Project Progress “Diary”
Keep up-to-date on progress, events and milestones related to the Airport Upgrade Project. Questions? E-mail us at AirportUpgrade@campbellriver.ca
| Date |
Phase/Event/Milestone |
| July 12, 2010 |
Runway construction begins. Runway threshold moves to 4000ft each day during construction hours: Mon-Sat, 7am -5pm.
|
| June 22, 2010 |
Council awards runway construction tender to Wacor Holdings Ltd. of Campbell River
|
|
June 7, 2010
|
NAV Canada begins work at the south end of the runway: Instrument Landing System (ILS) upgrade
|
|
May 18, 2010
|
City of Campbell River posts tender for runway extension work
|
|
Feb 24, 2010
|
Funding of $2.3 million granted to Campbell River by ICET for airport project
|
|
Oct 23, 2009
|
City Council gives formal approval to issue request for proposal (RFP) for airport project
|
|
Sept 25, 2009
|
Federal and Provincial government announce $8,331,250 funding for the project through Build Canada and the Infrastructure Stimulus Fund
|